[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953539":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953539,691,1,"单选题","建设项目工程任务实施的模式中，( )是指建设项目业主将全部施工任务发包给一个施工单位或由多个施工单位组成的施工联合体或施工合作体。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工合作体承包",false,{"key":16,"text":17,"correct":14},"B","平行发包",{"key":19,"text":20,"correct":21},"C","施工总承包",true,{"key":23,"text":24,"correct":14},"D","设计总负责","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目组织","建筑工程",0]