[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953533":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},953533,691,1,"单选题","建设项目工程任务实施的模式中，( )是指发包方根据建设项目的特点、项目进展情况和控制目标的要求等因素，将建设项目按照一定原则分解，将设计任务分别委托给不同的设计单位，将施工任务分别发包给不同的施工单位，各个设计单位和施工单位分别与发包方签订设计合同和施工合同。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","平行发包",true,{"key":16,"text":17,"correct":18},"B","施工总承包",false,{"key":20,"text":21,"correct":18},"C","施工联合体承包",{"key":23,"text":24,"correct":18},"D","施工合作体承包","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目组织","建筑工程",0]