[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953532":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},953532,691,1,"单选题","无论如何设置，考虑一般建设项目管理的目标和任务，业主方设置的管理部门都应该覆盖投资控制、进度控制、质量控制、合同管理、信息管理、组织与协调、安全管理等的项目管理工作任务，这是由项目管理的( )所决定的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期和目标",false,{"key":16,"text":17,"correct":18},"B","目标和任务",true,{"key":20,"text":21,"correct":14},"C","目标和性质",{"key":23,"text":24,"correct":14},"D","工作量","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目组织","建筑工程",0]