[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953529":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},953529,691,1,"单选题","下列单位中，( )是业主机构的延伸，全过程(从策划阶段一直到实施阶段)为建设项目业主服务，对项目的实施负责，与建设项目业主的目标和利益保持一致。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","PMC单位",true,{"key":16,"text":17,"correct":18},"B","CM单位",false,{"key":20,"text":21,"correct":18},"C","政府",{"key":23,"text":24,"correct":18},"D","工程咨询服务机构","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目组织","建筑工程",0]