[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953488":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953488,691,1,"单选题","对项目结构编码的相关表述中，不正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编码由一系列符号(如文字)和数字组成",false,{"key":16,"text":17,"correct":14},"B","编码工作是信息处理的一项重要的基础工作",{"key":19,"text":20,"correct":21},"C","项目的结构编码依据合同结构图，对项目结构的每一层的每一个组成部分进行编",true,{"key":23,"text":24,"correct":14},"D","一个建设工程项目有不同类型和不同用途的信息，为了有组织地存储信息、方便信息的检索和信息的加工整理，必须对项目的信息进行编码","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目组织","建筑工程",0]