[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953477":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953477,690,2,"多选题","建设项目建造阶段的主要任务是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","按工程建设计划和工程承包合同，组织工程施工",true,{"key":16,"text":17,"correct":14},"B","实行有效的管理和控制，完成项目建设任务",{"key":19,"text":20,"correct":21},"C","开展融资活动，落实建设资金",false,{"key":23,"text":24,"correct":14},"D","按相关规定组织项目竣工验收，将资产交付使用",{"key":26,"text":27,"correct":21},"E","落实水、电、气等工程施工条件","ABD","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]