[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953462":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953462,690,2,"多选题","实施准备阶段的回顾与评价的重点是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","评价项目前期工作的质量与合规性",false,{"key":16,"text":17,"correct":14},"B","实施过程中产生的主要变化、原因及其影响",{"key":19,"text":20,"correct":21},"C","各项准备工作是否充分",true,{"key":23,"text":24,"correct":14},"D","评价项目业主的组织能力与管理水平",{"key":26,"text":27,"correct":21},"E","开工前的各项报批手续是否齐全","CE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]