[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953454":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953454,690,2,"多选题","下列关于建设项目全面竣工验收的表述，正确的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","多数工业项目须在交付使用一段时间以后才进行全面竣工验收",true,{"key":16,"text":17,"correct":18},"B","全面竣工验收是单项竣工验收的基础",false,{"key":20,"text":21,"correct":14},"C","全面竣工验收应按谁投资、谁决策、谁验收的原则确定验收主体",{"key":23,"text":24,"correct":14},"D","对于大型或特大型项目，一般应组成竣工验收委员会进行验收",{"key":26,"text":27,"correct":14},"E","项目竣工验收委员会或验收组由项目业主负责组织","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]