[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953453":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953453,690,2,"多选题","为达到工程文档管理的目的与要求，确保工程文档的收集、整理、归档工作与项目的立项、准备、建设实施以及竣工验收同步进行，项目业主应当( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","明确档案管理分工",true,{"key":16,"text":17,"correct":18},"B","审议竣工验收报告",false,{"key":20,"text":21,"correct":14},"C","建立档案管理体系",{"key":23,"text":24,"correct":14},"D","统一档案整理标准",{"key":26,"text":27,"correct":14},"E","设立档案管理机构","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]