[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953443":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953443,690,2,"多选题","生产准备机构设立的时间，一般要根据( )进行统一安排。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","项目建设不同阶段的需求",true,{"key":16,"text":17,"correct":14},"B","生产技术的复杂程度",{"key":19,"text":20,"correct":14},"C","建设项目的性质、",{"key":22,"text":23,"correct":14},"D","项目建设进度",{"key":25,"text":26,"correct":27},"E","建设项目总体目标",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]