[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953440":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953440,690,2,"多选题","在项目实施过程中建立的生产管理体系主要包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","生产管理指挥体系",true,{"key":16,"text":17,"correct":14},"B","安全、环保管理体系",{"key":19,"text":20,"correct":21},"C","档案管理体系",false,{"key":23,"text":24,"correct":14},"D","原材料供应与检验体系",{"key":26,"text":27,"correct":14},"E","产品营销和市场开拓体系","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]