[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953434":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953434,690,2,"多选题","下列与建设项目内部控制要求相符的是( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","内部控制目标要同建设项目总体目标保持一致",true,{"key":16,"text":17,"correct":14},"B","内部控制要贯穿项目建设全过程，覆盖全部业务和事项",{"key":19,"text":20,"correct":14},"C","内部控制，要合理分解项目建设的目标和过程",{"key":22,"text":23,"correct":24},"D","内部控制的政策和程序不能随意变化",false,{"key":26,"text":27,"correct":14},"E","建设单位的内部控制要与各参与方内部控制相容","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]