[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953408":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953408,690,2,"多选题","对于工程变更，总监理工程师应按照施工合同的有关条款，在指定专业监理工程师完成( )等工作后，对工程变更的费用和工期作出评估。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定工程变更项目与原工程项目之间的类似程度和难易程度",true,{"key":16,"text":17,"correct":18},"B","确定工程变更项目与相关工程项目之间的类似程度和难易程度",false,{"key":20,"text":21,"correct":14},"C","确定工程变更项目的工程量",{"key":23,"text":24,"correct":18},"D","确定工程变更项目的范围",{"key":26,"text":27,"correct":14},"E","确定工程变更的单价或总价","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]