[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953406":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953406,690,2,"多选题","项目监理机构在审查工程延期时，应依( )确定批准工程延期的时间。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工合同中有关工程延期的约定",true,{"key":16,"text":17,"correct":14},"B","工期拖延和影响工期事件的事实和程度",{"key":19,"text":20,"correct":14},"C","影响工期事件对工期影响的量化程度",{"key":22,"text":23,"correct":24},"D","相关的法律、行政法规",false,{"key":26,"text":27,"correct":24},"E","工程建设的实际情况","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]