[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953378":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953378,690,2,"多选题","施工图预算审查的主要内容包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","技术经济指标水平",false,{"key":16,"text":17,"correct":18},"B","施工工程划分的合理性",true,{"key":20,"text":21,"correct":18},"C","工程量清单",{"key":23,"text":24,"correct":18},"D","预算单价的确定",{"key":26,"text":27,"correct":18},"E","有关项目费用及其计算","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]