[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953371":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953371,690,2,"多选题","实施准备阶段的进度控制任务包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","确定项目工期总目标",true,{"key":16,"text":17,"correct":14},"B","确定建设项目各阶段的任务和计划",{"key":19,"text":20,"correct":21},"C","初步编制建设项目的总进度计划",false,{"key":23,"text":24,"correct":14},"D","编制施工详图的供图计划",{"key":26,"text":27,"correct":14},"E","调研、分析和判断施工现场的条件和环境","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]