[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953369":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953369,690,2,"多选题","进度计划的调整方法包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","改变工作的最早开始时间",false,{"key":16,"text":17,"correct":18},"B","改变工作之间的逻辑关系",true,{"key":20,"text":21,"correct":14},"C","将关键工作压缩为非关键工作",{"key":23,"text":24,"correct":18},"D","改变子项目工作延续时间",{"key":26,"text":27,"correct":18},"E","重新编制网络计划","BDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]