[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953368":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953368,690,2,"多选题","某工程双代号网络计划如下图所示，图中已标出各项工作的最早开始时间和最迟开始时间，该计划表明( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作1-3的总时差为1",true,{"key":16,"text":17,"correct":18},"B","工作2-5的自由时差为1",false,{"key":20,"text":21,"correct":14},"C","工作2-6的总时差为2",{"key":23,"text":24,"correct":14},"D","工作4-7的总时差为4",{"key":26,"text":27,"correct":18},"E","工作5-7为关键工作","ACD","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]