[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953366":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953366,690,2,"多选题","影响进度目标实现的主要因素归纳起来有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工条件不利",true,{"key":16,"text":17,"correct":18},"B","不可抗力",false,{"key":20,"text":21,"correct":14},"C","设计变更的影响",{"key":23,"text":24,"correct":14},"D","建设项目参与方的组织不当",{"key":26,"text":27,"correct":14},"E","资金保障不能满足进度计划要求","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]