[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953347":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953347,690,2,"多选题","关于投标人编制投标文件的合理时间，表述正确的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","依法必须进行勘察设计招标的项目，自招标文件开始发出之日起至投标人提交投标文件截止之日止，最短不得少于15日",false,{"key":16,"text":17,"correct":18},"B","建筑工程概念性方案设计投标文件编制一般不少于20日",true,{"key":20,"text":21,"correct":14},"C","大型公共建筑工程概念性方案设计投标文件编制一般不多于40日",{"key":23,"text":24,"correct":18},"D","建筑工程实施性方案设计投标文件编制一般不少于45日",{"key":26,"text":27,"correct":18},"E","招标文件中规定的编制时间不符合要求的，建设主管部门对招标文件不予备案","BDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]