[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953344":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953344,690,2,"多选题","根据《中华人民共和国招标投标法》和《工程建设项目招标范围和规模标准规定》，( )项目的施工，必须采用招标方式发包。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","大型基础设施的",true,{"key":16,"text":17,"correct":14},"B","公用事业的",{"key":19,"text":20,"correct":14},"C","使用国有资金投资项目的施工单项合同估算价在200万元人民币以上的",{"key":22,"text":23,"correct":14},"D","使用国际组织援助资金的项目总投资额在3000万元人民币以上的",{"key":25,"text":26,"correct":27},"E","受自然地域环境限制的",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]