[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953334":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953334,690,2,"多选题","施工阶段和验收阶段的工程设计管理工作包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","组织设计交底",true,{"key":16,"text":17,"correct":14},"B","控制和审查设计单位提交的设计变更",{"key":19,"text":20,"correct":21},"C","组织设计单位参加完工验收、投运前的大型建筑物安全鉴定",false,{"key":23,"text":24,"correct":21},"D","向设计单位提出对工艺设施的改进建议、完善生产工艺和生产条件的意见",{"key":26,"text":27,"correct":21},"E","参加试运行","AB","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]