[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953326":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953326,690,2,"多选题","工程勘察阶段，建设单位项目管理的工作内容包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","主持研究和审查确认勘察方案",false,{"key":16,"text":17,"correct":18},"B","编制勘察任务书，拟定工程勘察工作计划",true,{"key":20,"text":21,"correct":18},"C","委托勘察单位，签订工程勘察合同",{"key":23,"text":24,"correct":18},"D","审查勘查工作纲要",{"key":26,"text":27,"correct":18},"E","监督协助勘察工作","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目实施","建筑工程",0]