[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953314":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953314,690,1,"单选题","关于建设单位对施工准备阶段的管理的表述中，错误的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","办理规划、建设等报建、施工放线测量和工程开工前的各项手续",false,{"key":16,"text":17,"correct":14},"B","审批工程监理单位编制的监理规划和审核项目监理部编制的监理实施细则",{"key":19,"text":20,"correct":21},"C","检查工程质量保证体系、安全保证体系的运行情况",true,{"key":23,"text":24,"correct":14},"D","审核工程监理单位审批后上报的承包人的施工组织设计","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]