[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953299":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953299,690,1,"单选题","建设单位和施工单位应按照\"三同时\"的要求，以( )形式将环保工程设施的施工建设进展情况上报政府环境保护行政主管部门，接受环境保护部门的检查。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","日报",false,{"key":16,"text":17,"correct":14},"B","月报",{"key":19,"text":20,"correct":21},"C","季报",true,{"key":23,"text":24,"correct":14},"D","年报","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]