[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953277":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},953277,690,1,"单选题","下列关于建设项目竣工验收范围的表述，错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","凡新建、扩建、改建的基本建设项目，符合设计文件所规定的内容及验收标准的应及时组织验收",false,{"key":16,"text":17,"correct":18},"B","对于因少数主要设备短期内不能解决，虽然工程内容尚未全部完成，但可以投产或使用的工程项目应组织竣工验收",true,{"key":20,"text":21,"correct":14},"C","按规定内容已经建设完成，但因外部条件制约，而不能投入使用的项目可以进行竣工验收",{"key":23,"text":24,"correct":14},"D","对于已经形成部分生产能力，但近期内不能按原设计规模续建的项目，在报主管部门批准后，可以缩小规模，对已完成的工程和设备，应组织竣工验收","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]