[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953272":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953272,690,1,"单选题","下列关于物资准备时机的表述，错误的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设项目所需物资应在建设项目竣工验收前落实供应渠道",false,{"key":16,"text":17,"correct":14},"B","应在建设项目竣工验收前签订供货合同",{"key":19,"text":20,"correct":21},"C","在项目建设前期，应根据物资的数量、规格以及品种特点和要求，分期分批组织进货，为投产试运行做好物质准备",true,{"key":23,"text":24,"correct":14},"D","大宗原料、燃料、材料的供货来源应在项目建设前期确定","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]