[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953266":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},953266,690,1,"单选题","试生产考核的目的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在满负荷运行状况下，考核生产工艺流程、指标参数是否能够保持稳定、连续、长周期运行",true,{"key":16,"text":17,"correct":18},"B","打通生产工艺流程、稳定生产运行状态",false,{"key":20,"text":21,"correct":18},"C","完善自控仪表控制系统",{"key":23,"text":24,"correct":18},"D","达到设计生产指标的最终目标","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]