[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953264":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},953264,690,1,"单选题","单机无负荷试车调试的条件不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","试车范围内的工程已按设计内容和质量标准完成，资料齐全",false,{"key":16,"text":17,"correct":14},"B","单机试车方案已报经批准",{"key":19,"text":20,"correct":14},"C","测试仪表、工具、记录表格齐备，维护人员就位",{"key":22,"text":23,"correct":24},"D","试车方案中规定的工艺指标已确认并下达",true,"",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]