[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953242":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},953242,690,1,"单选题","尾工工程超过项目投资总概算( )的，不能编制建设项目竣工财务决算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5%",true,{"key":16,"text":17,"correct":18},"B","10%",false,{"key":20,"text":21,"correct":18},"C","15%",{"key":23,"text":24,"correct":18},"D","20%","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]