[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953234":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953234,690,1,"单选题","下列关于项目资本金验资的表述，错误的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目资本金以货币资金出资的，应按照建设项目开户银行实际收到的资金和日期作为投资者投入资本的入账依据",false,{"key":16,"text":17,"correct":14},"B","项目资本金以实物或无形资产作为出资的，应按照投资协议或合同确定的价值作为投资者出资入账的价值",{"key":19,"text":20,"correct":21},"C","项目资本金以实物出资的应以实物转移的时间作为出资入账的时间",true,{"key":23,"text":24,"correct":14},"D","项目资本金以无形资产作为项目资本金出资的，应在投资协议或合同中确定其价值并规定完成有关手续的时间确认为出资入账时间","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]