[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953210":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953210,690,1,"单选题","工程风险是指建设项目实施过程中，因( )而引起的实际结果与预期结果的差异及可能性。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","外部条件的制约",false,{"key":16,"text":17,"correct":14},"B","决策的局限性",{"key":19,"text":20,"correct":21},"C","项目本身和环境条件的不确定性",true,{"key":23,"text":24,"correct":14},"D","工程变更","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]