[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953194":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953194,690,1,"单选题","总监理工程师应就工程变更费用及工期的评估情况与( )进行协调。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":14},"B","设计单位",{"key":19,"text":20,"correct":21},"C","承包单位和建设单位",true,{"key":23,"text":24,"correct":14},"D","建设单位和设计单位","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]