[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953192":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953192,690,1,"单选题","设计单位对原设计存在的缺陷提出的工程变更，应( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","提交总监理工程师",false,{"key":16,"text":17,"correct":14},"B","由总监理工程师组织专业监理工程师审查",{"key":19,"text":20,"correct":21},"C","编制设计变更文件",true,{"key":23,"text":24,"correct":14},"D","按规定报有关部门审定","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]