[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},953188,690,1,"单选题","监理单位发布的停、复工令应当事先向业主报告，如在紧急情况下未能事先报告时，则应在( )h内向业主作出局面报告。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":18},"B","24",true,{"key":20,"text":21,"correct":14},"C","48",{"key":23,"text":24,"correct":14},"D","72","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]