[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953173":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},953173,690,1,"单选题","下列关于工程变更的表述，错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在总监理工程师签发工程变更单之前，承包单位不得实施工程变更",false,{"key":16,"text":17,"correct":14},"B","未经总监理工程师审查同意而实施的工程变更，项目监理机构不得予以计量",{"key":19,"text":20,"correct":14},"C","在建设单位和承包单位未能就工程变更的费用等方面达成协议时，项目监理机构应提出一个暂定的价格，作为临时支付工程进度款的依据",{"key":22,"text":23,"correct":24},"D","总监理工程师应就工程变更的质量、费用与承包单位进行协商，无需取得建设单位授权",true,"",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]