[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953171":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},953171,690,1,"单选题","下列不属于工程款竣工结算监理基本程序的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程承包单位按施工合同规定填报竣工结算报表",false,{"key":16,"text":17,"correct":18},"B","专业监理工程师进行现场计量",true,{"key":20,"text":21,"correct":14},"C","建设项目业主审核后向承包单位付款",{"key":23,"text":24,"correct":14},"D","总监理工程师审定竣工结算报表，与建设项目业主、工程承包单位协商一致后，签发竣工结算文件和最终的工程款支付证书，报建设项目业主","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]