[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953147":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},953147,690,1,"单选题","竣工结算要有严格的审查，一般要考虑的方面不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","核对合同条款",false,{"key":16,"text":17,"correct":14},"B","关键工序，关键部位检查记录",{"key":19,"text":20,"correct":14},"C","落实设计变更签证",{"key":22,"text":23,"correct":24},"D","按图核实工程数量",true,"",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]