[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953146":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},953146,690,1,"单选题","建设项目业主根据项目功能目标的调整提出的工程变更不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程范围",false,{"key":16,"text":17,"correct":14},"B","建设内容的变更",{"key":19,"text":20,"correct":14},"C","工艺技术方案的变更",{"key":22,"text":23,"correct":24},"D","现场施工条件变化的变更",true,"",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]