[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953140":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953140,690,1,"单选题","里程碑进度计价支付方式，一般在( )合同中使用，其关键是合同双方确定工程进度款支付的里程碑进度和每个里程碑进度的支付金额和比例。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","纯单价",false,{"key":16,"text":17,"correct":14},"B","可调单价",{"key":19,"text":20,"correct":21},"C","固定总价",true,{"key":23,"text":24,"correct":14},"D","成本加酬金","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]