[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953130":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953130,690,1,"单选题","某下水管道项目进行赢值分析，原始项目估算为50050元，在某时点的已完工作的预算费用为7600元，已完工作实际费用为7700元，计划工作预算费用为7800元，根据对项目状况的分析，则项目总成本的新估算为( )元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","43009",false,{"key":16,"text":17,"correct":14},"B","50609",{"key":19,"text":20,"correct":21},"C","50709",true,{"key":23,"text":24,"correct":14},"D","50809","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]