[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953129":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},953129,690,1,"单选题","建设项目的某项工作，在某时点的计划工作预算费用为1000万元，已完工作的预算费用为1500万元，已完工作实际费用为1800万元，则此时的进度偏差( )万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","-300",false,{"key":16,"text":17,"correct":14},"B","-500",{"key":19,"text":20,"correct":14},"C","300",{"key":22,"text":23,"correct":24},"D","500",true,"",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]