[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953128":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},953128,690,1,"单选题","对后续工作及工期影响的具体分析方法不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","判断判断进度偏差是否影响关键工作",true,{"key":16,"text":17,"correct":18},"B","判断进度偏差是否在关键线路上",false,{"key":20,"text":21,"correct":18},"C","判断进度偏差是否大于总时差",{"key":23,"text":24,"correct":18},"D","判断进度偏差是否大于自由时差","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]