[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953127":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},953127,690,1,"单选题","一般有几个重叠的分项工作，每个分项工作有不同的工作计量单位的任务适合用( )测量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","费用比率法",false,{"key":16,"text":17,"correct":18},"B","加权单元法",true,{"key":20,"text":21,"correct":14},"C","监督人员评价法",{"key":23,"text":24,"correct":14},"D","渐进里程碑法","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]