[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953125":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953125,690,1,"单选题","为实现建设项目的总进度计划，编制与总进度计划相适应的各类资源需求和供应计划，属于进度控制的( )措施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织",false,{"key":16,"text":17,"correct":14},"B","管理",{"key":19,"text":20,"correct":21},"C","经济",true,{"key":23,"text":24,"correct":14},"D","技术","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]