[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953124":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},953124,690,1,"单选题","关于关键工作和关键线路的表述，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","网络计划中总时差为零的工作为关键工作",false,{"key":16,"text":17,"correct":18},"B","一个从始点到终点全部由关键工作所组成的线路为关键线路",true,{"key":20,"text":21,"correct":14},"C","一个从始点到终点全部由关键节点所组成的线路为关键线路",{"key":23,"text":24,"correct":14},"D","时差为最大值的节点串联起来的即为关键线路","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]