[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953120":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},953120,690,1,"单选题","对于非肯定型的网络计划，对应于计划评审技术(PERT)，当含有高度的不确定性工作项目时，可采用( )估算各项工作的持续时间。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","定量计算法",false,{"key":16,"text":17,"correct":14},"B","经验估算法",{"key":19,"text":20,"correct":14},"C","单一时间估计法",{"key":22,"text":23,"correct":24},"D","三时估算法",true,"",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]