[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953119":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},953119,690,1,"单选题","在工程网络计划中，工作w的最早开始时间为第28d，其持续时间为9d。该工作有三项紧后工作，它们的最迟开始时间分别为第40d、第43d和第48d，则工作w的总时差为( ) d。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":14},"B","12",{"key":19,"text":20,"correct":14},"C","5",{"key":22,"text":23,"correct":24},"D","3",true,"",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]