[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953118":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953118,690,1,"单选题","当项目进度延误或某个里程碑进度不能按时实现的情况下，为了加快进度，通常的做法是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","将关键工作变为非关键工作",false,{"key":16,"text":17,"correct":14},"B","改变关键线路上各工作之间的先后顺序",{"key":19,"text":20,"correct":21},"C","压缩关键线路上有关工作的持续时间",true,{"key":23,"text":24,"correct":14},"D","重新编制网络计划","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]