[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953117":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},953117,690,1,"单选题","当缺少项目的工作详细信息时，可以采用( )估算工作的持续时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定量计算法",false,{"key":16,"text":17,"correct":18},"B","单一时间估计法",true,{"key":20,"text":21,"correct":14},"C","经验估算法",{"key":23,"text":24,"correct":14},"D","三时估算法","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]